NORECO II – Power Interruption
A series of power interruptions will hit Dumaguete the next couple of days. The scheduled brownouts of NORECO II will be on the following days:
September 16, 2014 – 8:30 A.M – 5:00 P.M
From crossing Junob & Cantil-e the whole way up to Cantil-e and Bajumpandan road.
September 17, 2014 – 8:30 A.M – 12:00 N.N
SSS Building Bagacay to Mangnao Elementary School
September 17, 2014 – 1:30 P.M – 5:00 P.M.
Bajumpandan Road to Dumaguete City Slaughterhouse
NORECO II will clean the power-lines from overgrows vegetation
September 20, 2014 8:00 A.M. – 5:00 P.M
Amlan, Tanjay & Pamplone
The national Grip Corporation of the Philippines will have scheduled maintenance of the transmission line between Amlan & Guihulungan.
Sunday, September 21, 2014 – 8:00 A.M. – 5:00 P.M.
All areas in Dumaguete supplied by the Bagacay Substaition are affected by this NORECO II power interruption
In Valencia will be no power in Bong-ao & East Balabag
Bacong will suffer inform no power in Banilad, Sac-sac and SPI
Dauin, Siaton and Zamboanguita will also be without electrical power
NGCP will replace rotten poles and corroded insulators of the 69KV power-line.
how about at Brgy. Pulantubig Areas, are they affected for the said brownout on Sunday, Sept. 21, 2014?
Hi Bobby,
According to the NORECP II press release Pulantubig is not affected by the power interruption on Sunday.